Skip to main content

Construction Chemical

Anti Termite Treatment, Pre & Post Construction Termite

Cement and Its Properties

CEMENT

Cement is a binding material mixed with water and aggregate to form concrete or mortar.The mixture of cement and water is called Cement paste..The mixture of cement,water and fine aggregate is called mortar.The mixture of cement,water,fine and coarse aggregate is called Concrete or the mortar fill the voids in the presence of coarse aggregate is called Concrete.



Testing of Cement :- OPC & PPC


  1. Field test
  2. Laboratory test

1. Field test:-

  • Take a look at cement paste, there should not be visible lump.
  • Colour of cement should normally be greenish grey.
  • It should give a cool feeling,when we put hand into the cement bag.
  • Take a pinch of cement bag, it should give a smooth feeling.
  • feel not oily when touched.
  • Take a handful of cement and throw it on a bucket of full of water, the particle should float for some times before they sink.

2.Laboratory test:- Test of OPC: 33,43 and 53 grade 

Ordinary Portland Cement- As per BIS 
  • Ordinary Portland Cement, 33 Grade- IS 269:2013
  • Ordinary Portland Cement, 43 Grade IS 8112:2013
  • Ordinary Portland Cement, 53 Grade- Specification, IS 12269:2013

  •         Ordinary Portland Cement, 43 Grade IS 8112:2013

CHEMICAL / PHYSICAL
SPECIFICATION
REQUIREMENT AS PER
REQUIREMENTS
CLAUSE No.
IS No. 8112 – 2013



AMENDMENT No. 6
CHEMICAL REQUIREMENTS :
5

(Test Method IS : 4032 -1985)


(i)  Ratio of Percentage of Lime to
5.1
Not Greater than 1.02
percentage of silica, alumina and iron oxide

And not less than 0.66
CaO – 0.7SO3


---------------------------------------------------


2.8 SiO2 + 1.2 Al2O3 + 0.65 Fe2O3


(ii)  Ratio of percentage of alumina to that
5.1
Not less than 0.66
of iron oxide



(iii)  Insoluble residue, percent by mass
5.1
Not more than 4.0
(iv)  Magnesia, percent by mass
5.1
Not more than 6.0
v)  Total sulphur calculated as Sulphuric
5.1
Not more than 3.5
Anhydride (SO3), Percent by mass


Total loss on ignition
5.1
Not more than 5%
Chloride, percent by mass
5.1
Not more than 0.1
PHYSICAL REQUIREMENTS :
6

( Test Method IS :4031-1988


FINENESS :
SP. SURFACE
6.1
Not less than 225 m2/kg




SOUNDNESS :

6.2

a) Le-chatelier method

Not more than 10 mm
Expansion



b) Auto clave test expansion

Not more than 0.8%
SETTING TIME
6.3

a) Initial Setting time in Minutes

Not less than 30
b) Final Setting time in Minutes

Not more than 600
COMPRESSIVE STRENGTH
6.4

72  ± 1 Hours
(3 Days)

Not less than 23 MPa
168 ± 2 Hours
(7 Days)

Not less than 33 MPa
 672 ± 4 Hours (28 Days)

Not less than 43 MPa


 Note
*  Not more than 58 MPa



  • IS 1489(Part 1):1991 Specification for Portland pozzolana cement Part 1 Flyash based
CHEMICAL/PHYSICAL
SPECIFICA
REQUIREMENT AS PER IS
REQUIREMENTS
TION
No.1489(PART – I):1991 AMENDMENT

CLAUSE No.
No.3




CHEMICAL REQUIREMENTS:
6



(Test Method IS : 4032-1985)




(I). Loss of Ignition by mass, Max.
6.1
5.0


(II). Magnesia, Percent by mass Max.
6.1
6.0

(III). Sulphuric Anhydride (SO3),
6.1
3.0

percent by mass, Max.

(IV). Insoluble residue, percent by
6.1
x +
4(100-x)


mass,Max.

100


(x= where x is the


(V). Declare % of Fly Ash #
5 & 9.1
declare % age of fly ash )
Not less than 15 % and Not more than 35 %
(VI). Chloride, percent by mas #
9.2
Not more than 0.1 %
PHYSICAL REQUIREMENTS:
7



( Test Method IS : 4031 – 1988)







:
7.1
Not less than 300 m2/ kg
(I). Fineness: Specific surface



(II). Soundness :
7. 2



(a). Le-Chatelier Expansion Method

Not more than 10 mm

(b). Auto clave Expansion

Not more than 0.8 %




(III). Setting Time:
7. 3
30 minutes, Min.
(a) Initial Setting Time





(b) Final Setting Time

600 minutes, Max.
(IV). COMPRESSIVE STRENGTH
7.4



:




16 MPa, Min.
72 +/- 1 Hours (3-Days)

168 +/-2 Hours (7-Days)

22 MPa, Min.
672+/-4 Hours(28-Days)

33 Mpa, Min.
(V). Drying Shrinkage
7.5
Not more than 0.15%







Thanks for watching Blog

Comments

Popular posts from this blog

Anti Termite Treatment, Pre & Post Construction Termite

A.T.T  is the treatment given to the structure to protect it against Attack by subterranean termites, using a suitable chemical. The   chemical barrier   is a layer of soil in contact with the structure that has been suitably treated with approve chemical, so as to form an impervious barrier to kill that termites The following procedure of anti termite treatment to be done at the project site are based on IS 6313: 2001 The surface of the ground should be clean, compacted and firm. it should be free from any organic impurities. Safety goggles,  gloves  and face mask should be readily available at the site. The person conducting the anti termite treatment should be trained and should be wearing all the above safety gear during the operation. preliminary moisturing should be done when the soil is Sandy, loose and porous because the chemical solution may be lost due to percolation. The chemical treatment of the soil should start only after the fo...

ARCHES

An arch is a curved structural member consisting of a number of wedged shaped brick or stone blocks joint together with mortar and spanning on opening to support the weight above.

Reinforcement

RCC slab Plane structural members which are used as floor and roof covering in a building. The thickness of the slabs looking is quite small as compared to other dimensions. Classification of the slab:-  On the basis of the ratio of longer span to shorter span. RCC slab classified into the following two types  One- way slab  Two-way slab One way slab:-  The slab in which the ratio of   (Ly/Lx) longer span to short span   is greater than or equal to 2 are called one-way slabs. These slabs are also called edge supported slabs Slab supported on four edges also behaves as one-way slab if the ratio of longer span to shorter span is greater than or equal to 2. In these slabs bending take place only along the shortest span. Therefore, the main reinforcement is provided along the shorter span and distribution Steel is provided along with the largest span. Reinforcement in one way slab:-  Main reinforcement:- Reinforcement i...