Anti Termite Treatment, Pre & Post Construction Termite

Anti Termite Treatment, Pre & Post Construction Termite


A.T.T  is the treatment given to the structure to protect it against Attack by subterranean termites, using a suitable chemical. The chemical barrier is a layer of soil in contact with the structure that has been suitably treated with approve chemical, so as to form an impervious barrier to kill that termites


The following procedure of anti termite treatment to be done at the project site are based on IS 6313: 2001



  • The surface of the ground should be clean, compacted and firm. it should be free from any organic impurities.
  • Safety goggles,  gloves  and face mask should be readily available at the site.
  • The person conducting the anti termite treatment should be trained and should be wearing all the above safety gear during the operation.
  • preliminary moisturing should be done when the soil is Sandy, loose and porous because the chemical solution may be lost due to percolation.
  • The chemical treatment of the soil should start only after the foundation trenches and pits are ready for concrete.







  • Treatment should not be given when the soil is wet due to rains or sub-soil water.
  • In the waterlogged area, dewatering should be done and the chemical emulsion should be applied when the soil is absorbent.

Treatment of RCC foundation:-




  • The procedure of treatment, the chemical used and the dosage shall be mentioned for the masonry structure. Treatment need not be started from the bottom of the excavation pit
  • Open excavation:- Holes of depth 300 mm, spaced at 150 mm Centre to Centre is made by driving rod into the ground(20mm).The solution is then spread over the area as per manufacturer instruction (Normally 7.5l/m2)







Treatment on top of plinth filling:-



  • The top surface of the consolidated earth made in the plinth wall shall be treated with chemical emulsion at doses rate of 5l/m2.
  • If the top surface of this earth is rammed and prevents the emulsion from seepage easily than holes of diameter 12 mm, 50 to 75 mm depth that should be made using Steel rods at a spacing of 150 mm center to center to help the emulsion saturate the soil.


After construction

  • After the chemical treatment is given for horizontal surface, whether further concreting will have to be done, it should be cover with LDPE sheet as a separation layer.
  • The person doing the treatment should wash thoroughly before eating or drinking water, to avoid any unwanted physical hazards



Safety precautions:-

  • The direction of the wind has been checked before spring the chemical the person doing the treatment should not face the wind.
  • Accidental absorption of the chemical through the skin can cause poisoning.
  • Chemical should be stored in a separate area.
  • The chemical or the emulsion should be kept away from any source of fire, flame or heat.








Comments

Popular posts from this blog

ARCHES

An arch is a curved structural member consisting of a number of wedged shaped brick or stone blocks joint together with mortar and spanning on opening to support the weight above.

Knapen system of drying walls

Principle of  Knapen system : A difference of 16 °C to 24 °C is required to displace the vitiation air from a building by means of a vertical air shaft. The Knapen Tube : The method of fixing the Knapen tube in the wall. it is a simple porous tube which is fixed with its mouth inclined outwards. As the tubes are porous the moisture of penetrates inside them. Due to difference of temperature the dry air enters in the tube from its top portion as indicated by arrow. This dry air evaporates the moisture and saturated air comes out from the lower portion of the tube. This circulation of air is due to perfectly natural laws, and remains continuous till there is any moisture left in the wall.

Trigonometric formulas - Free Math Help

I always had trouble in calculating the angles because I did not remind the table that's why I had trouble in calculating the angle by the table. All my friends remembered the table but it was difficult to me to  pass the exam paper without angle, so I started harassing my teacher and asked him, "Sir, there is no other way or method  ." He helped me and make a  short trick with his help. That trick I tell you You have always used this table Another method  We can Calculate the angle by the left and right method .   As you know these are  some basic angle 0 °    30 °     45 °    60 °     90°  These are five angles that we get out of Eg sin30 °, sin45 ° etc Tan45 °, tan 90 °, tan30 ° etc. Cos0 ° cos30 ° etc  You just have to remember three formulas (L = left) (R = right) 1. SinΦ = √L / 4  2.cosΦ = √R / 4  3. TanΦ= √L / R  With example Suppose we have to find the value of sin30 ° Formula is   sin = √L / 4 Le